Author Archives: admin

Water Tower update

The foundation preparation required a full day to set up the ‘bolt boxes’. As the photo below shows, a piece of plywood with 4 holes corresponds to the holes in the tower legs. The long bolts with large square washers are fitted inside waxed cardboard cones and tightened up. The cones are sealed to the plywood with a caulked sealer. These 4 ‘bolt boxes’ are accurately positioned within the steel reinforcement in height and to fit the pattern of the 4 tower legs. Cross bracing was installed to ensure no movement before the concrete arrived.

Another day and fortunately a dry one we were ready for the concrete. The specification for the concrete was a ‘strong’ mix given by the structural engineers. We opted to use a local company who mix the exact amount required on site. This means you don’t over or under order. The delivery was a little late so we used the time to dig the foundation pad for the steel access ladder for the water tower.

With the cross braces removed the concrete was poured while we stood around and watched.

Note the vertical plastic pipe in the foundation, this is a duct for the water supply. Finally, when the concrete was poured and tamped down, we all stood for a team photo. Thanks to all the volunteers who helped.

The next step is to dig the foundation for the water crane, install the wooden shuttering and add the steel reinforcement ready for the next concrete pour. When that is completed, we have to build a blockwork plinth for the water crane.

Peak Railway Association Funded Water Tower at Rowsley

May 10th 2023

Work started at Rowsley on May 3rd for the excavation for the foundations.

The hole for the foundation was dug in a morning. A service duct was installed for the mains water supply and marker pegs installed to get the correct depth on stone. Eight 1 tonne bags of Type 1 MOT stone was levelled and compacted, but we soon realised that more would be required.

This brought an end to the first day, thanks to Mick, Clive, David and Martyn with his telehandler.

Second day Tuesday May 9th.

With another 5 bags of stone delivered and the hire of the vibration plate collected by Harvey, the team completed the stone layer for the foundation.

The foundation design was specified by our structural engineer. The steel reinforcement was ordered a few weeks ago and was installed on 50mm concrete spacers. The shuttering was installed and the boards backfilled.

The next stage is to install the hold down bolts in the steel reinforcement and get the concrete poured.

During a lunch break one of the team asked how much it had cost and did we get any quotes for labour. The team over 2 days work have saved almost £3000 in labour costs. All materials used so far have been sourced from within 20 miles of Rowsley which is in line with our policy using local suppliers.

Water tower project

It was mentioned at the Peak Railway Association AGM in May 2022 that they will fund a water tower and crane at Rowsley. Since then, it has turned into a collaboration of support for the railway. A generous donation from the family of Mike Shelton, a steam loco driver who served on the railway for many years started the funding. The remainder of the money will come from the donations made to the Peak Railway Association by their members when they renewed their subscriptions over the last few years.

The Braithwaite water tank and water crane were donated to the Derwent and Wye Valley Railway Trust some time ago, and they have given permission to use them on this project as a permanent loan.Some years ago, when the idea of this project first started the design of the tower was engineered on computer aided design (CAD) by a member and volunteer Andrew Treves. At the same time the water tank was refurbished. Andrew has dusted off the design and updated it, and in the process checked the latest standards and confirmed the structural calculations. The design, calculations and foundation design were passed to the civil engineering company Engineering Consultancy Services Limited (ECSL) who have certified the design on our behalf. This company is well known to Peak Rail as they conduct the necessary inspections of our infrastructure. Anyone watching Railway Architecture programmes on TV may have seen one of their directors Dave Gent talking about bridge structures.

The water tower structure is like a big Meccano set as most of it is bolted together. The vertical legs are a welded assembly which is 6 meters long, just under 20 feet. We will be looking at the most cost-effective way forward and hope to utilise the workshop facilities at Rowsley. Another consideration is what is the best surface protection we can have for the structure to minimise the future maintenance.

The positioning of the water tower will be at the end of the Rowsley platform on the Darley Dale side. The water crane will be next to it. Peak Rail has two identical water cranes available, both of which came from Mold junction. The intention is to refurbish the one currently in store at Rowsley for the project. The other water crane can be seen on the Peak Railway land behind Aldi in Buxton.

The order for the steel work has been placed with a company in Buxton in April for a delivery in July / early August. At the beginning of May the foundations were dug for the reinforced concrete raft.

This joint project of Peak Rail, Derwent and Wye Valley Railway Trust and Peak Railway Association is hopefully the start of a new beginning in taking the railway forward.

Jackie Statham

Book of Condolences

Please use the comments section below to leave your messages of condolence.

Thank You

Peak Rail receives Government’s Culture Recovery Fund

Peak Rail plc to receive £114,000 from second round of the Government’s Culture Recovery Fund

  • Peak Rail plc is among more than 2,700 recipients to benefit from the latest round of awards from the £1.57 billion Culture Recovery Fund 
  • This award covering the period from April to June 2021 will help enable Peak Rail plc with the costs it faces as its starts to welcome back visitors and volunteers and makes the transition towards a full re-opening.
  • This project is funded by the Culture Recovery Fund for Heritage. The Culture Recovery Fund is being delivered by The National Lottery Heritage Fund and Historic England, using funds provided by the Department for Digital, Culture, Media and Sport.

Peak Rail plc in Derbyshire has received a grant of £114,000 from the Government’s £1.57 billion Culture Recovery Fund to help the organisation recover and reopen.

Nearly £400 million has been awarded to thousands of cultural organisations across the country including Peak Rail in the latest round of support from the Culture Recovery Fund, the Culture Secretary announced today.

Peak Rail is a heritage railway, operating both nostalgic steam and diesel trains through the Derbyshire countryside from Rowsley South to Matlock Platform 2. The railway is mostly operated by a loyal and dedicated band of volunteers and is home to various railway groups who help and support the railway.

This award will help sustain the railway over the coming months until we can run at our full capacity.

Over £800 million in grants and loans has already been awarded to support almost 3,800 cinemas, performance venues, museums, heritage sites and other cultural organisations dealing with the immediate challenges of the coronavirus pandemic.

This brings the Government’s total investment across grants, capital and repayable finance from the Culture Recovery Fund so far to more than £1.2 billion across over 5,000 individual cultural and heritage organisations and sites.

The second round of awards made today will help organisations to look ahead to the spring and summer and plan for reopening and recovery. After months of closures and cancellations to contain the virus and save lives, this funding will be a much-needed helping hand for organisations transitioning back to normal in the months ahead.

Culture Secretary, Oliver Dowden, said:

“Our record breaking Culture Recovery Fund has already helped thousands of culture and heritage organisations across the country survive the biggest crisis they’ve ever faced.

Now we’re staying by their side as they prepare to welcome the public back through their doors – helping our cultural gems plan for reopening and thrive in the better times ahead.” 

Jackie Statham, Managing Director of Peak Rail plc said:

“We are delighted to have been awarded this grant, which means we will be able to reopen the railway after a 12 month period of closure. Peak Rail is a valuable local heritage venue which attracts visitors and volunteers of all ages and this grant will enable us to continue offering those experiences as well as preserving our site for future generations. I would like to take this opportunity to thank both the Peak Railway Association and Derwent and Wye Valley Trust for their valuable input in helping us achieve this grant, together with the various groups and shareholders for their kind letters of support.”

 Ros Kerslake, CEO of The National Lottery Heritage Fund, said:

 “Spring is definitely here, bringing not only sunshine but that sense of optimism and hope for the future. We are all looking forward to heritage places and other visitor  attractions reopening and I am very pleased that we have been able to support DCMS in delivering this vital funding to ensure the UK’s heritage sector can rebuild and thrive, boosting local economies, creating jobs and supporting personal wellbeing.”

Duncan Wilson, Chief Executive of Historic England, said:

“The value of our heritage sites and the people who run them has been amply demonstrated, as they have provided an anchor for so many of us through the dark    days of the last year. Vital grants from the Culture Recovery Fund have helped them survive and will now help them recover, as the places we all cherish start to reopen in the months ahead.”

The funding awarded today is from a £400 million pot which was held back last year to ensure the Culture Recovery Fund could continue to help organisations in need as the public health picture changed. The funding has been awarded by the National Lottery Heritage Fund and Historic England as well as the British Film Institute and Arts Council England

Permanent Way Update 16/10/20

I’d not realised that my last update had been late July. Since then much has been achieved by the P-Way team meeting up every week on a Wednesday.

At Matlock Riverside the work completed in August and September has included:

  • Replacement of 11 sleepers underneath Point 3, which leads to the Headshunt, with new ones purchased by the PRA last year. A split and partially rotted timber revealed two Toads which were relocated to a safe location nearby. This in fact was one of a couple of piles of old sleepers deliberately left to rot away at Riverside to encourage wildlife.
  • Replacement of 7 life expired sleepers in the Platform line in the three panels of track immediately before Point 3. Again new sleepers used.
  • Replacement of 8 life expired sleepers towards the far end of the Headshunt. This time using the last of the good quality second hand sleepers from the P-Way stock in Rowsley Yard.
  • Removal and replacement of two sleepers acting as support beams for the platform boards at the north end of Riverside Station. It had been noticed that the Platform surface had dipped at this point and the condition of the two support beams was highlighted as the problem.

Further work has taken place at two of the farm crossings.

  • At Statham’s Crossing the two gates, which had been removed earlier, were replaced having been repaired in the Workshop at Rowsley. For the Up side new hooks were used to hang the gate directly onto the girder acting as a post. Both gates were chained shut with new number combination padlocks. The Office and farmer were given the chosen number code.
  • At Dick Smith’s Crossing the gatepost on the Down side had to be replaced. Previous efforts to dig out the remains of the post left in the ground had failed. By removing some of the concrete collar around it and a great deal of brute force the base of the post finally lifted out in pieces. An hour well spent? The new post was firmed in with large rocks to hold it successfully in place. With holes drilled for the new hooks the gate was re-hung and chained shut.

Whilst undertaking a visual inspection of all the bridges after Lockdown I noted a concern regarding Bridge 40. This bridge has two girders between the abutments supporting longitudinal sleepers with the rail. There is support bracing between the girders. There are also three pairs of Bullhead rail either side of the track and between it, also from one abutment to the other. On top of these have been laid Crossing Timbers to cover what otherwise would be a drop into Warney Brook. The concern highlighted was the condition of the timbers in the 4ft and on the Down side walkway. All the timbers in the 4ft have been replaced and a start made on the walkway. The replacements have so far come from the ex Derbyshire Dales Narrow Gauge Railway. The timbers were once under a Point near the station. Ballast is also being reclaimed from the same location.

New timbers have been dropped off ready to replace those life expired under the Points at Rowsley.

All gauging measurements of the main line, loops and points was completed by mid August and recorded.

The team continues to work following current CV-19 regulations.

Roger Hallatt.

Unedited historic footage from The John Hilton Peak Rail Archives – Video 16/16

We have kindly been donated some photos and video footage by Mr John Hilton. In total there was 46 minutes of footage. So we’ve edited the footage into 15 films, which we are going to release over the coming weeks.

When we have released all 15 excerpts we will publish the final unedited video as produced and supplied by John.

We’d love to receive more old footage and/or photos of days and events gone by at Peak Rail that we can then share by adding it to our YouTube Channel. This we hope will help to preserve history and help us all remember days gone by.

Engine no. 29 – The John Hilton Peak Rail Archives – Video 15/16

Footage of Engine no. 29 taken at Peak Rail’s Mixed Traffic Gala held on August 11th, 2019, one of many special events held at Peak Rail during the spring and summer season.

Background to footage: We have kindly been donated some photos and video footage by Mr John Hilton. In total there was 46 minutes of footage. So we’ve edited the footage into 15 films, which we are going to release over the coming weeks.

When we have released all 15 excerpts we will publish the final unedited video as produced and supplied by John.

We’d love to receive more old footage and/or photos of days and events gone by at Peak Rail that we can then share by adding it to our YouTube Channel. This we hope will help to preserve history and help us all remember days gone by.

Engine no. 72 – The John Hilton Peak Rail Archives – Video 14/16

Footage featuring Engine no.72. Engine no.72 can be seen between March and October running between Peak Rail’s three stations in the Derbyshire Dales, Rowsley South, Darley Dale and Matlock. There’s also a Santa Special running every weekend and everyday during the Christmas holidays. There are extra trains during the February half term and special events with guest locomotives all throughout the spring and summer season.

Footage background: We have kindly been donated some photos and video footage by Mr John Hilton. In total there was 46 minutes of footage. So we’ve edited the footage into 15 films, which we are going to release over the coming weeks.

When we have released all 15 excerpts we will publish the final unedited video as produced and supplied by John.

We’d love to receive more old footage and/or photos of days and events gone by at Peak Rail that we can then share by adding it to our YouTube Channel. This we hope will help to preserve history and help us all remember days gone by.